Your bill of materials tells Business Central what you build. Your routing tells it how. Get both right and costing, purchasing and scheduling start working for you. Get either wrong and every production order inherits the mistake.
Why BOMs and routings matter most
Every other manufacturing function in Business Central reads from these two records. MRP uses the BOM to calculate what to buy. Production orders copy the BOM and routing to tell the floor what to do. Costing multiplies BOM quantities by item costs and routing times by work center rates. Capacity planning loads your work centers based on routing times.
If your BOM says six bolts and the floor uses eight, purchasing runs short and your margin report lies. If your routing says six minutes and the real run time is eleven, your schedule looks fine on paper and fails on the floor.
The return on investment we covered in How Discrete Manufacturers Achieve 209% ROI with Business Central starts with data this accurate. Clean structures give you the inventory accuracy, cost visibility and reliable schedules that the numbers depend on.
Production BOM or assembly BOM: which do you need?
Business Central offers two kinds of BOM. They look similar but serve different jobs.
| Question | Production BOM | Assembly BOM |
|---|---|---|
| Typical use | Items you make on a production order | Items you assemble from stock components, often to order |
| Routing and capacity | Uses routings, work centers and machine centers | No routing. Uses assembly orders and a simple lead time |
| What goes on the lines | Items and other production BOMs | Items and resources |
| Where you run it | Production orders | Assembly orders |
Most discrete manufacturers need production BOMs. Use assembly BOMs when you build finished goods from stock components with little or no shop routing, such as kits or configure-to-order products.
How a production BOM works
A production BOM has a header and lines. The header carries the number, description, unit of measure and status. Each line is either an item or another production BOM. That second option is how you build multi-level structures.
Watch these line fields closely:
- Quantity per. How much of the component you use for one unit of the parent.
- Scrap percent. The expected loss at that line. MRP and costing include it, so your purchasing covers the real need.
- Routing link code. Ties the component to a routing operation so it consumes at the right step.
- Starting and ending dates. Control when a line is active.
Status controls what you can use
Every BOM carries a status of New, Under Development, Certified or Closed. Only certified BOMs work on production orders. That rule protects you from running work against a structure engineering has not approved.
Versions protect your history
When a design changes, create a new version instead of editing the live BOM. Each version carries its own lines, status and starting date. Business Central picks the version that applies on the order date, so you can schedule a design change without rewriting history.
Before you change or retire a component, run the Where-Used function. It shows every parent BOM that uses the item.
HP-200 Hydraulic Pump Assembly
-
HP-200Hydraulic pump assemblyFinished item1 each
-
HP-210Pump housingNested production BOM1 each
-
RM-1010Aluminum casting1 each
-
HW-2040Mounting bolt2% scrap6 each
-
-
HP-220Rotor kitNested production BOM1 each
-
RM-1180Steel shaft1 each
-
HW-2210Bearing2 each
-
-
HW-3005Seal kit1 each
-
How a routing works
A routing is the ordered list of operations needed to make an item. Each operation points to a work center or machine center and carries four times: setup, run, wait and move. Business Central uses those times to schedule the order, load capacity and calculate cost.
- Work center. A group of capacity such as an assembly cell or paint line. It holds a calendar, capacity, unit cost and overhead rate.
- Machine center. A specific machine inside a work center, with its own efficiency and rate.
- Serial or parallel routing. Serial routings run operations in order. Parallel routings let operations run side by side.
- Routing link code. Matches BOM components to operations so material consumes at the right step.
- Status and versions. Routings use the same New, Under Development, Certified and Closed statuses as BOMs. They support versions too.
| Operation | Description | Work center | Setup (min) | Run (min per unit) | Components consumed |
|---|---|---|---|---|---|
| 10 | Assemble housing | ASM-01 | 15 | 6 | RM-1010, HW-2040, HW-3005 |
| 20 | Install rotor kit | ASM-02 | 10 | 8 | RM-1180, HW-2210 |
| 30 | Pressure test | TST-01 | 20 | 5 | None |
| 40 | Pack and label | PCK-01 | 5 | 2 | None |
How BOMs and routings connect on the item card
A BOM and a routing do nothing until you attach them to an item. On the item card, set Replenishment System to Prod. Order. Then choose the Production BOM No. and the Routing No.
Check three more settings while you are there:
- Manufacturing Policy. Make-to-Stock builds to forecast and reorder points. Make-to-Order builds against demand.
- Flushing Method on component items. Choose Manual, Forward, Backward, Pick plus Forward or Pick plus Backward to control when consumption posts.
- Costing Method. Standard, FIFO or Average. This decides how BOM and routing data turn into inventory value.
Set up BOMs and routings in seven steps
Order matters. Follow this sequence and you avoid the rework that slows most manufacturing go-lives.
- Build your capacity first. Create work centers and machine centers. Assign calendars and set capacity, efficiency and rates. A routing cannot exist without them.
- Create the routing. Add operations in sequence with setup and run times. Use times from observed production, not engineering estimates.
- Build production BOMs from the bottom up. Start with the lowest-level subassembly. Nest it inside its parent through a production BOM line.
- Add routing link codes. Match each component to the operation that consumes it.
- Certify. Set the status to Certified on every routing and BOM you plan to use.
- Attach to item cards and roll up cost. Set the replenishment system, BOM number and routing number. If you use standard costing, run the standard cost roll-up so the item picks up cost from both records.
- Test before you trust. Create a simulated production order and refresh it. Review the components, operations and calculated cost. Then compare the result against a real job from your floor.
How BOMs and routings drive product cost
Business Central builds the cost of a manufactured item from two sources.
- Material cost comes from the BOM. It multiplies each component quantity by its unit cost and includes scrap.
- Capacity cost comes from the routing. It multiplies setup and run time by the work center or machine center rate and adds overhead.
Add the indirect cost percentage and you get the rolled-up cost of the item. With standard costing, wrong quantities or times show up as variances. With average or FIFO costing, they distort your unit costs and margins. Either way, you see the problem in your reports long after the root cause sits in a setup record.
Six mistakes that wreck costing and scheduling
- Editing live BOMs instead of using versions. You rewrite history for every future order. Use versions with starting dates.
- Entering engineering time instead of real time. Standard times from a design sheet rarely match the floor. Time a few real runs and use those numbers.
- Ignoring scrap. Zero scrap looks clean and guarantees shortages. Add realistic scrap percentages to lines and operations.
- Skipping routing link codes. Components consume at the wrong operation or on the wrong date. Your inventory and work in process drift from reality.
- Building top down. Start at the lowest level so every nested BOM is certified and ready before its parent.
- Letting engineering and ERP BOMs drift apart. If a CAD or PLM system holds a separate BOM, decide who owns it and how changes reach Business Central.
Where add-ons fit
Standard Business Central handles BOMs, routings, costing and MRP. Many manufacturers add tools for what happens next, such as shop floor data collection, graphical scheduling and finite capacity views. Partners such as Insight Works build add-ons for these needs.
For more on planning and scheduling, read our posts on MRP in Microsoft Business Central and the Graphical Scheduler for Business Central.
Frequently asked questions
What is a bill of materials in Business Central?
A bill of materials (BOM) lists the components and quantities you need to make one unit of an item. Business Central uses production BOMs for manufactured items and assembly BOMs for items you assemble to order. The BOM drives material planning, production orders and product cost.
What is the difference between a production BOM and an assembly BOM?
A production BOM supports items you make on production orders with routings, work centers and capacity planning. An assembly BOM supports items you assemble from stock components on assembly orders, with no routing. Most discrete manufacturers rely on production BOMs.
What is a routing in Business Central?
A routing is the ordered list of operations needed to make an item. Each operation names a work center or machine center and carries setup, run, wait and move times. Business Central uses routings to schedule production, load capacity and calculate labor and machine cost.
Do you need Business Central Premium for bills of materials and manufacturing?
Yes. Bills of materials and manufacturing capabilities, including production BOMs, routings, production orders and capacity planning, require the Business Central Premium license. Confirm current licensing details with your Microsoft partner before you plan your rollout.
Can Business Central handle multi-level BOMs?
Yes. You build multi-level structures by nesting one production BOM inside another. Business Central rolls material and capacity cost up through every level so the parent item carries the full cost.
How do you change a BOM without disrupting production?
Use BOM and routing versions with starting dates. Business Central picks the version that applies on the order date, so new orders pick up the change while you decide how to handle open orders. Production orders copy the BOM and routing when you create or refresh them.
How do BOMs and routings affect product cost?
The BOM supplies material cost from component quantities and unit costs. The routing supplies labor and machine cost from operation times and work center rates. Together they produce the rolled-up cost of the item.
Get your structures right before go-live
Clean BOMs and routings are the foundation of every manufacturing implementation. iCepts Technology Group has helped distributors and manufacturers since 1980 and implements one ERP: Microsoft Dynamics 365 Business Central. Bring us your current BOMs and we will show you how they translate.